What’s Happening at DSG | UW

WISPRINT40 Project Update – As with all projects, our team lead provides daily reports to the customer. Here is a sample of what a report looks like. We don’t rely on our reputation; we build it one project at a time.

  • Installed all horizontal cross supports to top horizontal top iron paster brackets. (x6).
  • Confirmed spacing of horizontal supports.
  • Tightened all horizontal supports
  • Installed 4 of the six top irons on the pasters.
  • Installed all securing screws on under decking molding and tighten.
  • Mounted inch stop stations on top of mono units.
  • Met with electrician as to material that is needed to run all electrical cables on press.
  • Cleaned up tools and area.
  • Confirmed level of Paster 4. Straightened shims checked/set tram of Paster 4 to infeed.
  • Confirmed level of Paster 3. Straightened shims and checked/set tram of Paster 3 to Paster 4.
  • Confirmed level of Paster 2. Straightened shims and checked/set tram of Paster 2 to Paster 3.
  • Confirmed level of Paster 1. Straightened shims and checked/set tram of Paster 1 to Paster 2.
  • Reviewed installation schematics for complete electrical system and inspect electrical panels to locate termination points.
  • Mount inch stop stations on top of mono units.
  • Reviewed installation schematics for complete electrical system and inspect electrical panels to locate termination points.